AQW 29615/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to detail the budget set aside for the construction of the A5 Western Transport Corridor scheme between Strabane and Ballygawley during the (i) 2025-26; and (ii) 2026-27, financial years.

Asked by Peter McReynolds MLA on 1 July 2025

  • Answered
  • Written
  • After due date
  • Priority
Tabled
1 July 2025
Answer due by
9 July 2025
Answered
22 July 202521 days after tabling
Department
Department for Infrastructure
Priority question
Yes

Answer

The DfI budget for the A5 scheme for the 2025-26 financial year is £165m which is now subject to review. Budgets have not yet been agreed for the 2026-27 financial year, however, this remains an Executive flagship project. Annual budget allocations to the scheme will be subject to Executive and Assembly approval as part of the statutory budget process.