AQW 15987/22-27 Written question to the Minister for Infrastructure

To ask the Minister for Infrastructure to detail the amount of budget for the works on the (i) A2 Clooney Road, Ballykelly; and (ii) A29 Ring Road, Coleraine, has been spent on (a) road resurfacing; and (b) active travel provision.

Asked by Peter McReynolds MLA on 1 October 2024

  • Answered
  • Written
Tabled
1 October 2024
Answer due by
16 October 2024
Answered
16 October 202415 days after tabling
Department
Department for Infrastructure
Priority question
No

Answer

The value of the Active Travel scheme on the A2 Clooney Road in Ballykelly is £2.6m and the value of the scheme on the A29 Ring Road in Coleraine is £0.8m.

Provision of high quality active travel infrastructure along existing roads, in some cases means having to move and reprofile the existing carriageway, including replacing kerb lines and drainage. This is the case on the Clooney Road and Coleraine Ring Road schemes where the carriageway needs to be realigned and reprofiled to facilitate the active travel infrastructure improvements. The resultant resurfacing is a necessary consequence of delivering the active travel improvements and cannot, therefore, be considered in isolation.

The resurfacing element of the Clooney Road active travel scheme is estimated to be in the region £0.4m for the surface course material, with the Coleraine Ring Road estimated to be in the region £0.2m.

I can further confirm that the roads in question were not in a condition where carriageway resurfacing was considered a priority. It would not be practical to wait many years for road surfaces to deteriorate to the point where they would be prioritised for resurfacing before progressing any road improvement scheme, including improvements to active travel provision.

Official sources